top of page
P2-1-002.jpg

Provided project management and design services. This project involved the installation of over 1,000 feet of new gas lines and services, as well as the retirement of outdated and/or corroded gas lines. The covered area ranged from S. Dobson Ave. to S. Anthony Ave. (West to East), E. 83rd St. to E. 95th St. (North to South). It was broken into seven phases. Each phase included a design, review, peer review, final review submittal stage, and each phase also had custom restoration plans, and custom traffic control plans. Through each phase, the engineers held the drawings and designs to the highest standard.

PRIME

Jacobs

MARKET

Rail/Transit

SERVICE

Project Management & Design

LOCATION

Chicago, IL

CLIENT

CREATE/Metra